A peek into lessons learnt from Singapore Rail Transport Conference

SRTC

Attended by more than 20 international railway experts, the inaugural Singapore Rail Transport Conference (SRTC) held in November 2016 provided a platform for sharing and potential collaboration in the area of technology development and innovation among operators of some of the world’s busiest metro lines. SMRT gained valuable insights as we strive to enhance rail performance and reliability.

The conference also provided us with an opportunity where we could benchmark ourselves against regional transport providers like Hong Kong’s Mass Transit Railway (MTR). Here are some key learning points shared by two of our guest speakers.

“Not everything needs to be in-house”

Professor Alfred Huan, Chairman, SMRT Technical Advisory Panel stated that SMRT has taken on “the very ambitious task and programme to upgrade its own engineering capabilities”. He added that this includes the company’s efforts to digitise data and adopt digital technology to coordinate our operations and maintenance.

Professor Huan, who is also the Executive Director of the Institute of High Performance Computing at A*STAR pointed out that as SMRT continually builds up its network of expertise, “not everything needs to be in-house”.

“Instead SMRT can tap on expertise within Singapore’s good eco-system of universities, A*STAR, and other research organisations”, said Huan, who was also a guest speaker at the conference.

“The important thing for SMRT is to be able to understand how to integrate all the different expertise around to promote its own objectives.”

Hong Kong MTR Vs SMRT – Adopting industry best practices

Speaking to reporters on technology advancement on the side lines of the event, Professor Lee Kang Kuen, Professor for Transportation at the Hong Kong Polytechnic University, said both Hong Kong MTR and SMRT have adopted continuous condition monitoring. This is currently seen as one of the best practices in the industry.

“I can see in Singapore, SMRT is adopting the same drive as MTR in really going along with the industry best practises. With all these on-going efforts, there will be a quantum leap in reliability improvements,” he added.

Hong Kong MTR’s experience achieving a high MKBF

The HKMTR reached 520,000 mean-kilometres between failure (MKBF) in the first quarter of 2016 while SMRT aspires to achieve 400,000 MKBF by 2018.

Professor Lee shared his confidence that SMRT would be able to achieve its rail reliability targets by improving from our experiences and lessons learnt in our 30 year history.

“MTR started operations back in 1979, so it is actually about 10 years prior to SMRT. MTR has improved through lessons learnt over the years. For each lesson learnt we adopted improvement measures. This is how excellence can be built up. I’m sure that with the same approach being adopted by SMRT that excellence can be achieved here,” he said.

“Exchange of experiences not “import”

When asked by a reporter what aspects of the HKMTR could be imported to Singapore, Professor Lee pointed out that each network has its own features, and it is important to share experiences and not “import”.

The professor, who has over 40 years’ experience in railway Operations and Maintenance (O&M), projects and consultancy, also stressed the importance of having these sharing sessions regularly.

“I am actually very delighted that this (the conference) has been done quite well where member railways get to share their experience so other members will not repeat what has gone wrong,” he said.

SMRT Improvements to Rail Engineering Capabilities

A few days ago, a group of young engineers who were attending a one-week course as part of STEP-IN* programme came back to the main maintenance depot at Bishan to help their more senior colleagues investigate the root cause of a technical problem on the train fleet operating on the North-South and East-West Lines (NSEWL) and discuss the recovery plan. That day, we had a spate of train-related defects that caused three trains to be taken out of service, when these trains completed their regular service runs at terminal stations. This is what we call “stock change” or “planned withdrawal at terminal stations”.

Journey to raise, train and sustain a robust rail engineering capability

There is nothing unusual about a group of engineers coming back to the office to work until 3am. What is unusual is that, they came back on their own accord, without being told to so. In fact, I have given specific instructions to their bosses, not to disturb the participants of the STEP-IN programme unless it is an emergency, so that the participants can focus on the one-week course. In this case, there was no service disruption. Although there was a need to get to the bottom of the issue because it had the potential of becoming a fleet issue, we did have other engineers to deal with the immediate concern.

I know exactly what these engineers, who have been with us for not more than two years, went through, as they went about their discussions and investigations that night. It is no different from what I went through as an engineer in the air force for 23 years: root cause analysis, digging out historical records to understand previous maintenance work done on the affected trains and components, etc. The thought process and mantra have been drilled into them. These young engineers demonstrated a thirsty curiosity to find out why things happened. They listed down every possibility, without jumping to conclusions. They repeatedly asked why the fault occurred (in the same way one might peel an onion), not accepting a case of “No-Fault-Found” (NFF) even if the fault “Can Not be Duplicated” (CND) after the affected trains returned to the depot. There was, in the air that night, an all-consuming desire to get to the root cause, leaving no stone unturned. For them to act together in unity, I am sure there was also esprit de corps and a sense that we are in this together.

Building a Robust Rail Engineering Capability

When I first joined SMRT, I set a goal of building a robust rail engineering capability within SMRT Trains. To do so, we aim to strengthen three key areas: people, process and technology. Three and a half years on, this goal is still an on-going journey. The two areas of process and technology are straightforward enough, as part of SMRT’s rail improvement efforts.

To strengthen our processes, we adopt a life cycle approach to all our critical assets in trains, track, traction power, signalling and communication systems. Such an approach requires us to work closely with the Land Transport Authority (LTA) to better manage the timeliness of asset renewal for such hardware. Each renewal presents us with opportunities to improve the inherent design reliability, availability and maintainability (RAM) of the assets leveraging on the operational experience that our staff have accumulated over the past three decades. As part of process enhancement, we also decided to review our maintenance regime regularly over the asset life cycle. Instead of blindly following manufacturers’ maintenance manuals, the revised preventive maintenance tasks must take into account field experience and local operating context, such as asset age, utilisation patterns, environmental conditions and operational requirements.

To enhance the use of technology, we adopt a predictive maintenance approach. This means that we collect data and information on asset conditions and use analytical tools to project how long more the assets can last before they need to be replaced, what additional maintenance efforts are needed to ensure that the assets will continue to perform reliably until they are replaced. Traditional railway maintenance relies heavily on engineering hours to run specialised engineering vehicles on the rail network to collect these data and information. However, given the limited engineering window, the same track location is only surveyed once every few months. Today’s technology allows us to equip passenger trains with on-board sensors and survey the same track location at a much higher frequency. All these translate into opportunities for better maintenance performance.

Hardware and heartware

Hardware issues are being addressed through better work processes. At the same time, more extensive fielding of technology, such as railway condition monitoring devices, complement work processes so that maintenance and renewal efforts are done more efficiently and effectively.

But no less important is our drive to strengthen our heartware – our people. Indeed, the toughest and most complex part of building a robust rail engineering capability within SMRT Trains lies in the area of people development.

When we first started this journey three-and-a-half years ago, SMRT had about 180 rail engineers, and morale was low. Today, we have boosted the number to more than 400. Other than a small number of mid-careerists who have joined us, the majority of the new recruits are either fresh graduates from local universities or in their late twenties.

Numbers alone are not enough. We need to organise our technical workforce into a value chain spanning from maintenance and engineering, to plans and projects. Take for example, the Rolling Stock (this means trains in railway lingo) Engineering Centre. It has been organised into four departments: Rolling Stock Depot (RSD) and Rolling Stock Workshop (RSW), where staff perform maintenance and inspection tasks on trains and components respectively. With the data and information captured by RSD and RSW, Rolling Stock Engineering (RSE) staff analyse reliability trends and initiate engineering studies to review and improve reliability. Finally, Rolling Stock Project (RSP) staff follow up with the proposed reliability enhancement recommended by RSE and translate these recommendations into concrete plans by justifying for resource funding. They also follow through the plans by working closely with LTA to translate these plans into modification or renewal projects. When modified or renewed, the assets go back into the hands of RSD and RSW with a higher inherent reliability, availability and maintainability.

Participation in this cycle of value chain and staff rotation throughout the various parts of this value chain will not only allow our engineers to grow their competencies, knowledge, skills and experience, it will prevent silo thinking. Rotating in and out of all four departments means that all engineers will develop an empathy for the challenges facing their colleagues in other engineering centres. This not only allows us to deepen and broaden our rail engineering capability, it fosters the development of an esprit de corps.

I think this is value creation, and it is replicated in the other engineering centres in SMRT Trains: Signalling and Communication, Permanent Way, Power, Systems and Technology Integration, Integrated Facilities.

The right stuff

We have developed roadmaps for all three areas of people, process and technology. These are not just words and paper concepts. They are actions in different phases of execution. Following these roadmaps, we may well achieve a more robust rail engineering capability in SMRT Trains within the next few years. But, will it last? The life cycles of rail assets are measured in decades, not years. For it to last, I think we need to engender the right ethos and culture among our staff. Our newly recruited engineers must be groomed into good leaders, imbued with the right values and attitude so that they can set a good example for the rest of the technical workforce as they progress in their careers.

From this perspective, what happened a few days ago when the group of young engineers came back voluntarily to support a recovery effort is encouraging. I am heartened to see that these engineers have thoughts that lead them to curious and determined action to find root causes. In time to come, I hope that these actions will become habits across SMRT Trains. Working together with esprit de corps and over time, we can and will rewrite the destiny of SMRT Trains and the nation’s experience of the rail network.

“Watch your thoughts, for they will become actions. Watch your actions, for they’ll become… habits. Watch your habits for they will forge your character. Watch your character, for it will make your destiny.” – Margaret Thatcher

*SMRT Trains Engineering Professionalisation INduction or STEP-IN is an in-house five-year, on-the-job training programme in collaboration with local and overseas academic institutions. STEP-IN is conducted with short, regular doses of structured training to equip newly recruited engineers as they take their first steps into the rail industry with the necessary rail-related knowledge and experience. The programme is designed so that they can be accredited as chartered rail engineers at the end of their first 5 years with SMRT Trains. A related programme, STEP-UP, is intended for mid-career railway engineering staff to uplift their professional competencies after several years in the industry. Together, STEP-IN and STEP-UP develop railway engineering staff to their fullest potential.

SMRT Rail Performance Data

SMRT’s engineering team tracks closely the performance of all rail lines because the data collated allows the team to know which areas of the rail network need more attention.

Such data is shared with the public too. SMRT has been reporting quarterly statistics on the performance of the North-South and East-West Lines (NSEWL) on SMRT’s corporate website. Doing so allows commuters to keep track of key performance indicators for our rail system, such as delays of more than five minutes, disruptions of more than 30 minutes and the train withdrawal rate.

Data on MRT station assets

We have recently included data on the reliability of MRT station assets used by commuters, such as escalators, lifts and fare gates. We will continue to publish key service performance indicators on a regular basis so that you can follow our journey in improving reliability on our network.

The re-sleepering, re-signalling, third-rail replacement and power network improvement project will contribute to better reliability on the NSEWL – Singapore’s longest, oldest and most heavily-used rail lines.

The mean kilometre between failure (MBKF) rate will improve, thanks to stepped up our maintenance efforts. Furthermore, our multi-year, multi-project renewal efforts for the NSEWL are on track.

While we acknowledge that the improvement in NSEWL service reliability may not seem to be significant in the first 10 months of 2016, we are quietly confident it will demonstrate clear improvements in the coming years. The better MKBF numbers will translate to better journeys for commuters with trains that run more reliably, and shorter waiting times as more trains are deployed on the NSEWL.

How MKBF will be improved

We have been tracking the sources of our service delays over the past three years and classifying them into categories such as third-rail, signalling, traction power and various types of train-related faults. For each category, we have a series of initiatives in place to address these faults in the immediate, medium and long term.

Improvements in MKBF rate will be achieved as we complete each of these initiatives. For example, we had a number of third-rail-related incidents in the first 10 months of the year that resulted in planned service delays. These are delays of not more than 10 minutes caused by engineering work that the engineers needed to carry out during traffic hours whenever sensors installed on selected passengers trains pick up defects that have the potential of causing more than 30 minutes delays. As part of our short term improvement initiatives, the use of these sensors allow us to identify an emerging issue and nip it in the bud before it caused a longer delay and inconvenienced commuters even more. With the completion of third-rail replacement by March 2017, as part of our long term improvement initiatives, we expect that such incidents will be significantly reduced.

As of November 2016, 33% of delays lasting more than five minutes were signal-related. We expect these to reduce significantly after we successfully migrate our ageing signalling system to the new Communication-Based Train Control (CBTC) system. The CBTC system has a higher level of redundancies. The new signalling system will be activated on the NSL in 2017 and we are working hard to complete the EWL by end-2018.

We have intensified our efforts to renew the equipment that provides traction power to the network. There are also similar fleet-wide renewal of components to address propulsion, door and brake systems that constitute 90% of train-related delays.

All-out effort to improve NSEWL

These efforts take several years to complete because of the length of the NSEWL, and the size of the fleet. As we serve commuters nearly 20 hours a day, and 365 days a year, we have limited time to carry out renewal and maintenance works. For example, there are 188,000 30-year-old timber sleepers on NSEWL to be replaced. With 141 six-car trains and 24 doors on each train, there are 3,384 train doors for us to work on. Nonetheless, with a laser-sharp focus and a never-give-up determination to catch up with our counterparts in Hong Kong and Taipei, we believe that there is only one direction for NSEWL rail service reliability to go in the coming years: Up.

Commuters may wish to refer to Your Journey Matters – most recently updated in August 2016 and also available on our website– for a comprehensive primer on SMRT’s efforts to renew and improve the NSEWL.

Mercedes-Benz O405 – Fond Farewell

The Mercedes-Benz O405 Hispano was the workhorse in its heyday in the mid-1990s. Back in the days of Trans Island Bus Services (TIBS), 73 O405s were introduced into the fleet. The last remaining O405 was deregistered in September 2016. We pay homage to this classic bus model that has charmed many passengers and bus fans alike.

Senior Bus Captain (BC) Tan Boon Thian has been with SMRT since 1993 and he used to drive Service 960 from Woodlands to Marina Centre. Senior BC Tan drove the O405 for 15 years, long enough for him to recognise the bus by the noise the engine makes. “The buses were air-conditioned and were very stable,” he explained in Mandarin, adding that the O405 buses were much more comfortable compared to the old Nissan buses. “But the modern buses today are definitely more comfortable for the passengers.”

The O405 did have its drawbacks, despite being a very popular bus. “You have to have a certain body type to drive this bus. Too short and you can’t reach the pedal.” BC Tan also pointed to the steering wheel and then to his belly, “Too much here and you won’t fit in the seat”. Buses today have steering wheels that can be adjusted to the BC’s preference. While the O405 was still a very good bus, it was starting to show its age. The needs of the passengers were also changing. The O405 is not a wheelchair accessible bus and has been a training bus in recent years.

Senior Engineering Supervisor Mohamed Rafi Bin Syed Masood has been with SMRT since 2006 and has worked on O405 model servicing. From an automotive mechanic’s perspective, O405 is reliable because Auto Service has a strong maintenance regime. The new bus system is completely different from O405 and technicians are required to pick up more skills. The Preventive Maintenance team that services the buses are made up of five groups: Air Conditioning, Body, Undercarriage, Driveline and Vehicle Electrician.

Rafi can also identify the O405 just by the sound of the engine. “These buses are like my children. I have spent so many years with them. Of course I can tell how they sound like.” When comparing the O405 to the newer buses, Rafi felt that the old buses had their own character. “When you drive an old bus, it feels like driving a bus. Driving one of the newer buses feels like driving a car.” He was referring to how the older buses were slower to pick up while the new buses speed up quite easily.

Rafi said that he will miss the O405, “Old is Gold,” he said with a smile.

SMRT Rail Improvements – Updates

A tremendous amount of work is being put into renewing and upgrading the North-South and East-West Lines (NSEWL), Singapore’s oldest, longest and most heavily utilised MRT lines. The work takes place every day even as the rail network continues to serve passengers for around 20 hours a day and as the system copes with increased ridership. Following the inaugural publication in October 2015, Your Journey Matters – Edition 2 continues the story of SMRT’s rail transformation efforts on the NSEWL.

SLEEPER REPLACEMENT

Working closely with LTA and rail contractors, the SMRT team achieved a major milestone when we finished replacing wooden sleepers on the North-South Line (NSL) with concrete sleepers in April 2015. The NSEWL were built with wooden sleepers. These sleepers support the rails on which our trains run. Some 188,000 sleepers are nearing the end of their 25-year lifespan. Exposure to the sun and rain over the years, vibration from moving trains and the weight each sleeper has to bear when a train passes over it add to the wear and tear.

By renewing wooden sleepers with concrete sleepers that have a 50-year lifespan, journeys on the NSEWL will be safer and smoother for decades to come. Positive results from the sleeper replacement are already felt on the NSL. Journey times on the NSL have been reduced by around 10 per cent after the speed restrictions were fully lifted in May 2015.

Wooden sleepers along the East-West Line (EWL) are now being replaced nightly. Steady progress is being made thanks to the experience gained by our engineers while carrying out the NSL sleeper replacement project. When the work is completed by the end of 2016, passengers travelling from Pasir Ris to Joo Koon on the EWL will also experience smoother train rides.

RE-SIGNALLING

The project is progressing well with 98% of the NSL completed and 76% of the EWL re-signalling work done. We have started trials to test the new signalling system on the NSL. Re-signalling is expected to be completed on the NSL in 2017 and on the EWL in 2018.

The new signalling system will substantially improve the capacity of the NSEWL to run trains at shorter intervals. This would mean a shorter wait for trains, which would ease congestion at station platforms during peak periods. The capability will be maximised as the train fleet is progressively enlarged by end 2016 to allow more trains to be deployed on the NSEWL. More than half of the 57 new C151B trains for the NSEWL have been delivered by the middle of 2016. This underlines the importance of coordinating the multi-year, multi-project effort in rail renewal so that the combined benefits of these projects will give you a better journey on the rejuvenated NSEWL.

Under the re-signalling project, the new signalling system supplied by Thales will see one of the most advanced train signalling systems in the world installed on the NSEWL. The current signalling system, which dates back to the 1980s, keeps trains a safe distance from one another by dividing the rail network into fixed segments of track length called blocks, with only one train allowed into each block at any time. These blocks measure between 800m to 1,000m in length. This Fixed Block system protects passengers in one train from other trains operating along the same line.

The new signalling system uses advanced communications technology installed on trains to constantly update the traffic management system on the identity, location and speed of every train. The new system, which is more precise than the system it replaces, will lead to better use of the rail network because the footprint for each train, which includes the length of the train and the safety distance in front and behind the train, will be much smaller.

This Moving Block system can be imagined as a safety bubble that moves with and protects the train, and will automatically slow down when it approaches a train ahead. This shorter distance will allow us to deploy more trains at shorter intervals on the rail network while maximising safety for passengers. When fully operational, the new system will allow trains to be spaced 100 seconds apart, which is a significant improvement from the 120 seconds between trains under the current system. The new signalling system is also designed with more redundancies, which makes it more reliable because major disruptive signal faults are less likely to occur.

THIRD RAIL REPLACEMENT

SMRT passenger trains are powered by electricity supplied by a powered steel rail. This rail is called the Third Rail because it is fixed next to and slightly above the two running rails on which the train wheels travel. The Third Rail replacement project currently being carried out on the NSEWL marks the first network-wide replacement for the 200km-long NSEWL Third Rail since SMRT operations began in 1987. The trains draw electricity from the powered rails through Current Collector Devices (CCD) that make contact with the rail and transfer electricity to the train’s electrical system. Each six-car MRT train has 24 CCD shoes that are in constant contact with the Third Rail when in motion and even when it makes a stop at MRT stations.

Over the years, this constant contact adds to wear and tear of the Third Rail and the brackets that are used to support the weight of this steel rail. If the Third Rail sags due to worn out supports, power faults could occur. The Third Rail replacement project is timely as it will increase the reliability of the electrical system. The work involves turning off the power, unbolting the old Third Rails, replacing them with new ones and re-connecting the rails to the electricity network. We are making steady progress and expect to complete the work in early 2017.

UPGRADING OLDER TRAINS

The C151 Kawasaki Heavy Industries (KHI) train entered service in 1987 while the C651 Siemens was introduced in 1994. SMRT is upgrading the 19 C651 Siemens trains as they have logged a higher number of train faults compared to other train models. Singapore Rail Engineering has completed two prototype trains and will be proceeding with the upgrade works on the C651 trains.

When completed in 2018, the upgraded C651 Siemens trains will have new or refurbished train sub-systems such as new air conditioning, electric doors, brakes and propulsion systems. These have been the primary causes of delays due to train faults. Upgraded trains will also have sensors that furnish the Train Captain and engineering staff with the train’s state of health, thus making it easier to operate and maintain the train. The upgrade will include a makeover that gives our passengers a new-look cabin.

NEW TRAINS INCREASE PASSENGER CAPACITY

Thirty new C151B trains, part of a fleet of 57 new trains for the NSEWL, have been delivered to Bishan and Tuas Depots where the trains are being fitted out and will be tested extensively. These trains, designed to operate with the new signalling system, will allow more trains to be run on the NSEWL.

Before a new train enters operational service, SMRT’s engineering staff will work closely with LTA and the train manufacturer to get the new train ready. It takes about a year to do this. The work involves testing the air-conditioning, automatic doors and sensors, propulsion and brakes, communication equipment as well as interior fittings like seats, poles and handles. Every item will be rigorously tested before it is certified safe for passenger service. More new trains are on their way to Singapore and more than half of the 57 trains will be delivered by the end of 2016.

***

This is part of a series on SMRT’s rail improvement efforts. Read more:

Powering SMRT Trains on the North-South and East-West Lines
SMRT- Airconditioning Improvements
SMRT- Platform Screen Door Maintenance
SMRT- Escalator Maintenance

Eye on the future: Options for replacing or renewing the BPLRT system

The 8-hour disruption on the Bukit Panjang Light Rail Transit (BPLRT) on Wednesday 28 Sep 2016 shows that the ageing system continues to test the mettle of our engineering staff and the patience of users of Singapore’s first light rail system.

In March this year, we indicated that it is time to relook the BPLRT as the system is nearing the end of its design life. A joint team with the Land Transport Authority (LTA) is currently reviewing the future of the BPLRT system with a view to completely transform the light rail system. It will be more than just a makeover.

Options for renewal

Aware of the design limitations of a light rail system which uses trains designed to function as airport shuttles on flat, short distance commutes between airport terminals, SMRT would like to share the options available for renewing the system. There are three options for the future of the BPLRT. The system has been operational since 1999 and is fast approaching its 20-year lifespan in 2019.

Option 1: A people-mover like autonomous guided vehicles that travel on the existing viaducts but do not draw on external power.

Option 2: A new conventional LRT system but with significant design enhancements in key infrastructure like power supply, signalling system, rolling stock as well as track and station assets.

Option 3: Renewing the existing Bombardier system, keeping the AC power design but with a more advanced communications-based train control (CBTC) signalling system. The CBTC system will allow trains to be more accurately controlled by the operations control centre, allowing more trains to be operated on the network, while moving at faster speeds and closer headways if necessary. This means more people can take the trains and enjoy faster journeys.

The rejuvenated BPLRT will be based on proven technology which is cost-effective to operate over its design life.

The LTA-SMRT study team is also keeping track of the development and public transport services of Bukit Panjang town. This includes monitoring how the BPLRT system can be better integrated with heavy rail systems at the North-South Line and the Downtown Line.

Another idea involves doing away with the 10.5km long, 14-station LRT network. The idea is for people in the Bukit Panjang area to be served by enhanced bus services. This is not far-fetched as a fully loaded high capacity bus like a double-decker bus can take 130 passengers, which is more than the 105-person capacity of a single Bombardier CX100 train car used on the BPLRT. These train cars are paired during peak hours, doubling capacity to 210 passengers. However, replacing the light rail with an all-bus option may lead to more congestion on the roads.

The disruption last week has driven home the urgency of planning for the future. It is the latest incident that has put the BPLRT system in the media’s glare. The Straits Times said the Bukit Panjang Line “isn’t a paragon of reliability and its design makes it prone to glitches”.

Stop-gap measures to improve reliability

As we look to the future, SMRT engineers have also proposed short-term measures to boost the reliability of the legacy system.

Key areas identified for renewal include the signalling system, the trains and track infrastructure. The last item includes the rail brackets that have given rise to problems on the line. These renewals will address recurring reliability issues involving track faults, traction power faults and signalling issues.

Owing to reliability issues, the driverless LRT system is not living up to its name as Rovers have to be deployed at the stations, which were designed for unmanned operations.

Meanwhile, near-term repair and maintenance measures of the system are being stepped up. This includes increased day-to-day system manning, and speedier recovery plans in event of disruption.

Near-term measures

Among the measures the BPLRT team has done:
– Replacement of rail brackets with fortified design at critical portions of the track
– Load testing of trains to be conducted to confirm tractive capability to reduce power faults
– Adjusted motor controller settings for better power reliability
– Installed camera systems on the underframe of four train cars to monitor the interface between trains and rails

Deploying staff across the network expedited assistance to passengers on Wednesday 28 Sep 2016 when passengers had to detrain to track at BP1 Choa Chu Kang station in the morning and at BP6 Bukit Panjang station around 5pm that day. A total of 26 additional staff have been added to the BPLRT team to enhance response time and assistance to commuters.

The range of near-term measures should be complemented by an in-depth review of the BPLRT to future-proof the transport system. This will enable the future system to serve Bukit Panjang residents years from now by providing transport options for safe, reliable, comfortable journeys that are cost-effective to operate and maintain.

Excuse Chits

Some of you might have come across an article in The Straits Times today relating to the Circle Line service delays yesterday morning. A commuter shared in the article that SMRT should support commuters with breakdown slips which they can show their employers. We would like to share that we do provide excuse chits, as proof that commuters were delayed because train services were affected. These slips are readily available at our Passenger Service Centres. In the event that you need one, please approach our station staff.

SMRT Buses lends a hand to Go-Ahead Singapore

SMRT Buses is helping Go-Ahead Singapore cope with a shortage of drivers needed to run bus services in Loyang.

News of this development has surfaced a term which bus enthusiasts may already know. It’s called Interlining, which is the practice of having bus captains drive multiple routes. Interlining requires the driver to know the road network, road conditions and bus passenger travel patterns that are peculiar to each route he or she is assigned to drive. For instance, a route that includes schools may see a surge in passengers at various times of the day when students end their classes.

Mr Tan Kian Heong, Managing Director SMRT Buses and Road Services, explained why SMRT is stepping in to help another public transport operator, “SMRT Buses will support Go-Ahead Singapore to ensure that commuter journeys are not affected. Ten SMRT bus captains will be attached to Go-Ahead for two months to help with their current staffing needs.

Mr Tan also shed light on what interlining entails, “Interlining is often used to achieve an efficient scheduling solution. However, SMRT Buses is selective when applying interlining into our schedule because an excessively interlined arrangement would require bus captains to be familiar with multiple routes, which is more demanding than driving a single route. It may also have an impact on their work-rest cycle. For our interlined services, SMRT Buses will ensure that all bus captains receive route familiarisation training and cater for sufficient rest so that they can carry out their duties well. The welfare of our bus captains is important to us in maintaining high service standards.”

Powering SMRT Trains on the NSEWL

In October 2015, SMRT released the inaugural edition of Your Journey Matters, outlining SMRT’s rail transformation efforts. Almost a year later, we have published Your Journey Matters – Edition 2, which continues the story of SMRT’s ongoing efforts to improve and renew the North-South and East-West Lines (NSEWL) – Singapore’s oldest, longest and most heavily used MRT lines.

The multi-year, multi-project efforts described in Your Journey Matters underline SMRT’s commitment to serve you better. In this new edition, we also bring you updates on the ongoing station upgrades to escalators and platform screen doors, as well as a look into how the air-conditioning is maintained on our trains.

A tremendous amount of work is being put into renewing and upgrading the North-South and East-West Lines (NSEWL), Singapore’s oldest, longest and most heavily utilised MRT lines. The work takes place every day even as the rail network continues to serve passengers for around 20 hours a day and as the system copes with increased ridership.

The transformation of the NSEWL is a complex set of engineering projects. It represents the first major upgrade for the lines since they started operations in 1987. Indeed, the renewal of the NSEWL is said to be the biggest modernisation project on a “live” MRT system anywhere in the world.

This modernisation effort will lead to an updated and renewed railway system that will allow SMRT to run more trains, carry more passengers and serve our passengers better with faster connections across the MRT network. The multi-year, multi-project effort takes place seven days a week, all-year round. Much of the work takes place away from the public eye in train depots, deep underground in train tunnels or during the early hours of the morning when trains have stopped running. Progress is made every day to modernise the NSEWL to serve you better.

With just three hours every night for engineering staff to access the track when trains are not running, it is vital for SMRT to prioritise and allocate the engineering hours and resources properly across different projects. Since 5 June 2016, the implementation of later train service start times on Sundays for 13 stations along the East West Line have given the engineering team much needed additional time to work each night. These extra hours are maximised for urgent maintenance and repair tasks as well as upgrade and renewal projects.

Powering the North-South and East-West Lines

With more trains due to be added to the NSL and EWL, existing power cables have to be replaced with larger capacity cables to accommodate the increase in power demand. SMRT is working with LTA to address the rail network’s future power needs.

A number of measures are being implemented to minimise inconvenience to MRT passengers due to power-related faults. These measures tie in with recommendations made by the Independent Advisory Panel, approved by LTA, on rectification measures to improve the rail power supply system.

These measures include renewing power components that are nearing the end-of-life stage on the 30-year old network with completely new components, increasing the power capacity of the network and thirdly, improving the design of the power network.

In order to improve the design of the power network, Voltage Limiting Devices will replace the existing 64P Earth Fault Relay. Works will be done on the 750V DC Switchgear & DC Cables, Direct Current Group (Rectifiers and Inverter) and High Voltage Group (AC Switchgear & HV cables) in order to renew, upgrade and increase the power capacity.

***

This is part of a series on SMRT’s rail improvement efforts. Read more:
SMRT- Track Improvements
SMRT- Airconditioning Improvements
SMRT- Platform Screen Door Maintenance
SMRT- Escalator Maintenance

SMRT Third Rail Maintenance to Prevent Disruptions

The third rail supplies electrical power to the trains operating on the rail line. It is elevated and runs parallel to the rest of the track. A part of the train known as the Current Collection Device (CCD) is in constant contact with the third rail through a component called the CCD shoe. If you imagine the third rail to be similar to the wall socket at home, the CCD is the plug. However, in the context of a train, the “plug” is sliding along a very long “socket”. As such, the alignment of the elevated third rail has to be very precise in order to power the trains at all times.

SMRT Conditioning Monitoring Device_LVDT

The Linear Variable Displacement Transducer (LVDT) helps monitor the alignment of the third rail. The LVDT measures the movement of the CCD shoe and through this data, the system can chart the precise height of every inch of the third rail.

Engineers compare the latest graphs with earlier ones to identify locations where the height of the third rail was recorded as too low, or where the height has changed too much from the last measurement. With this info, the Permanent Way maintenance team can quickly zoom in, inspect and rectify any potential Third Rail faults relating to misalignment.

SMRT Conditioning Monitoring Device_LVDT Graph

With the LVDT technology, the frequency of third rail inspection is increased and real time detection is possible, even during service hours. The degradation trend of the third rail can also be tracked.

The LVDT is the first of a few other condition monitoring devices we will be sharing on this blog. Check back again soon to find out more about the technologies we use to make maintenance of the track as efficient as possible.